To download our brochure please click on the link below :
Inflation Instructions :
Step 1
Load first lightly against bulkhead. Load each successive row tightly against previous row.
Step 2
Last units placed against sides of trailer. Void should not exceed 46 cm. Fill excess void with other appropriate filler material.
Step 3
Always use proper material to protect bags from load face. No sharp edges or points may touch bag. Irregular load surfaces may require rigid buffering material. Buffering material must cover entire area of load face.
Step 4
Before attaching tip to valve, inspect BOTH tip and valve for damages.
Step 5
Attach tip by pressing down over valve. Hold air bag in place until pressure builds up. A single air bag will stabilize the load. Inflate bag until the load is pressed against the sides. Do not try to reposition bag once inflated. CAUTION... DO NOT OVER – INFLATE bag.
Step 6
Position bag 5 cm above floor. Inflated bag should cover at least two thirds of face and height of load. Level 5 bags may be used in voids up to 46 cm. Level 1;2;3-4 bags should be used in voids from 31 cm to 46 cm.
Step 7
Check air pressure once air bag is in place and inflated.